Interview with Bozhinovska: Started from zero, now we have gas connection with Greece and Serbia, MEPSO investments, interconnection with Albania
- The new gas connections with Greece and Serbia, investments in MEPSO, the interconnection with Albania, the planning of energy capacities, and support for vulnerable households are among the priorities of the Ministry of Energy, Mining, and Mineral Resources. In September and early October, these activities also gained a strong international dimension through the country joining the Vertical Gas Corridor and regional ministerial cooperation.
- Post By Angel Dimoski
- 15:53, 11 October, 2026
Skopje, 11 October 2026 (MIA) - The new gas connections with Greece and Serbia, investments in MEPSO, the interconnection with Albania, the planning of energy capacities, and support for vulnerable households are among the priorities of the Ministry of Energy, Mining, and Mineral Resources. In September and early October, these activities also gained a strong international dimension through the country joining the Vertical Gas Corridor and regional ministerial cooperation.
With Minister Sanja Bozhinovska we spoke about the benefits of these projects, the new laws, the responsibilities of the institutions, and the economic value of domestic resources. She also touches upon the creation of the Ministry from the very beginning, as well as the accusations with which Levica justifies the motion of no confidence against the Minister that is on the agenda for the end of this month.
Over the past month, you have been active both domestically and at regional energy meetings. What specific results would you highlight, and what will they mean for citizens and companies?
The most important thing is that we are working simultaneously on the infrastructure, investment rules, and direct support for citizens. The new energy links should provide more supply options, a stronger grid to support economic development, and programs for vulnerable consumers to help families for whom energy costs represent the greatest burden.
In September, in Thessaloniki, we formalized our accession to the Vertical Gas Corridor. Together with Serbia, we are entering a broader regional framework that connects the gas systems of nine countries. This is significant because our interconnectors acquire a broader European function: they open access to new sources and create the opportunity for Macedonia to participate in gas transit as well.
In Belgrade, in early October, we continued with the second ministerial meeting of Macedonia, Serbia, Greece, and Bulgaria. This quadrilateral format, initiated in May, establishes regular cooperation between two EU member states and two candidate countries. We are connecting the discussions with the specific tasks of the operators, project deadlines, and the support we need for European energy integration.

On the domestic front, I would highlight the resolution of the long-standing property issue regarding the Dubrovo substation. Upon my initiative, we intensified the coordination between the competent institutions and MEPSO, and the facilities have been registered as the company's property. This provides a stronger legal basis for investments in this important part of the transmission network.
In September, we also announced over 500 new inverter air conditioner vouchers for vulnerable categories of citizens. These build upon the distribution of 4,070 vouchers from the previous call, which we are implementing this year. In parallel, we are evaluating initiatives for new energy facilities and working on legislative solutions for geology and mining.
In each of these areas, the goal is for the result to have practical value: more secure supply, predictable conditions for businesses, and support that reaches the citizens.
The public often confuses the responsibilities of the Ministry, ESM, MEPSO, NOMAGAS, and ERC. Where does your direct responsibility lie, and why is this division important?
The division is established by law and must be respected. The Ministry prepares energy policies, legislative solutions, and development plans, conducts procedures within its jurisdiction, and implements support programs. We are also responsible for policies in mining, geology, and mineral resource management, as well as the coordination of energy investments.
Regarding companies, the Energy Law makes an essential distinction. Article 134 establishes that the Ministry is the owner of the electricity transmission system operator, MEPSO, and Article 205 establishes ownership of the gas transmission system operator, NOMAGAS. In those companies, we exercise statutory ownership powers, while their management and supervisory bodies make operational decisions in accordance with the law.
ESM is owned by the Government. The Ministry does not manage ESM, does not conduct its tenders, and does not make its commercial decisions. Articles 133 and 204 regulate ownership unbundling, meaning the separation of transmission system management from generation and supply. This is the principle known as "unbundling," designed to ensure independent operators and equal access to networks.
Precisely because of this separation, I do not participate in government decision-making on issues where the Government exercises its ownership rights in ESM. This practice is also documented in the MEPSO certification procedure. Respecting that boundary is a legal obligation.
ERC is an independent regulatory body. According to Article 48 of the Energy Law, its president and members are appointed and dismissed by the Parliament. The Ministry does not appoint them nor dictate their decisions. Regulatory decisions on prices and tariffs are made within the scope of ERC's authorizations, and ESM determines its electricity sales offer through the appropriate procedure.
My responsibility for energy policy is clear. The responsibility of every board of directors, supervisory board, operator, and regulator must be equally clear. Only in this way can the public receive an accurate answer as to who made a specific decision and who is accountable for it.
MEPSO is taking on a greater role in your activities. What is changing in the transmission grid, and what benefits will the shunt reactor in Dubrovo bring?
The transmission grid is the foundation for any serious development ambition in the energy sector. If we want new production capacities, a stronger industry, and greater exchange with our neighbors, we need a grid that can securely handle that load. That is why we are directing our work with MEPSO toward investments, the removal of administrative obstacles, and long-term planning.
Dubrovo is a concrete example of how institutional initiative can resolve a long-standing issue. This concerns a 400/110 kilovolt substation, built in 1977, which is significant for domestic supply and cross-border connections. At my initiative, we opened the question of its property status and stepped up coordination with MEPSO and the competent institutions. Through joint work, we succeeded in having the facilities registered as the company's property.

For me, it is important that such problems are resolved. Regulated property status strengthens legal certainty and creates better conditions for investing in state infrastructure. That is work that may not be seen immediately on an electricity bill, but it is essential for the system to develop.
The installation of a shunt reactor is also planned in Dubrovo, with its commissioning scheduled for early 2027. This is equipment that helps control voltage in the transmission system, especially during periods of lower consumption when overvoltages can occur. By absorbing excess reactive energy, the reactor contributes to more stable voltage conditions and protects the equipment.
In addition, the reconstruction of the control building in Dubrovo is part of a broader project encompassing three 400/110 kilovolt substations and five 110 kilovolt ones. Work is also underway on the property and legal issues in Bunardzhik, which are important for the planned Bunardzhik–Miladinovci power line, as well as on the preparation of the master plan for grid development.
The interconnection with Albania is also of particular importance, via the 400-kilovolt power line from Bitola toward the Albanian border and the connection to Elbasan. This project complements the regional connectivity of our system and creates conditions for a greater exchange of electricity. MEPSO is the bearer of its implementation, and the Ministry provides support within the scope of its competencies.
Through these activities, we are preparing the grid for new production, the needs of the industry, and the regional market. This is a long-term investment in supply security.
How far along are the gas interconnectors with Greece and Serbia, and why are you working in parallel on the gas market and the potential use of hydrogen?
With these projects, we are expanding Macedonia's ability to choose where and from which direction it is supplied. Our previous dependence on a single entry gas connection limits our flexibility. Connecting with Greece, and subsequently with Serbia, creates conditions for access to multiple sources, to LNG terminals via the Greek system, and to the broader European market.
The interconnector with Greece is under construction. In Belgrade, I reported that about 30 out of the total 67 kilometers of the Macedonian section have been welded. The goal is completion in 2027, with an initial capacity of 1.5 billion cubic meters per year. We are carefully monitoring the dynamics because welding is followed by other construction, technical, and testing activities.
In July, together with representatives of NOMAGAS and the Greek operator DESFA, we conducted a joint inspection of the route. This visit was preceded by working meetings with the management of both operators. The joint assessment was that the project is progressing and that conditions exist for intensified momentum. Such direct coordination helps resolve problems in a timely manner and harmonizes the work on both sides of the border.
A design and construction contract worth EUR 29.4 million has been signed for the Macedonian section of the interconnector with Serbia. It envisions 22.4 kilometers, bidirectional flow, and a capacity of 1.4 billion cubic meters annually. Connecting the southern and northern routes also opens up the possibility for our country to play a transit role.
In parallel, at the initiative of the Ministry, we set in motion the process for establishing a natural gas market operator through MEMO. In September, the Government adopted the relevant conclusions. The Ministry is coordinating the preparation because infrastructure must be accompanied by an organized market, clear rules, and conditions for competition.
We are also planning the new gas connections with an eye toward the next generation of technologies. The interconnector with Greece is designed for future hydrogen transport, and such readiness is also envisaged for the connection with Serbia. In July, we completed the first comprehensive national Hydrogen Study, with technical assistance funded by the EU through IPA II and the Western Balkan Investment Framework. It examines the production, transport, storage, and use of green hydrogen. So, today's investments are being aligned with the future needs of the industry and the European energy market.
This year you have held meetings in Washington, Vienna, Geneva, and Pristina, as well as in Greece and Serbia. How do these contacts translate into concrete support for Macedonia?
We conduct international cooperation with a clear domestic agenda. We need more secure supply sources, financial and technical support for infrastructure, new technologies, and partners who understand our development priorities. When you establish such an agenda, meetings gain continuity and concrete next steps.
In Washington, in April, we signed a memorandum with the US to enhance the security of natural gas supply. We spoke with representatives of the US administration and with Chevron regarding diversification and cooperation opportunities. This created an additional foundation for the work on regional gas connections and discussions with potential partners.

In Vienna, as part of the government delegation, we presented the opportunities for economic and energy cooperation. In September, we continued that work at the Macedonian-Austrian Business Forum in Skopje, focusing on topics such as grid modernization, energy storage, and energy efficiency. In Geneva, during meetings within UNECE, the focus was on sustainable resource management and expert cooperation.
In Pristina, we participated in the work of the Energy Community and discussed advancing our bilateral partnership. The talks in Delphi with DESFA regarding the gas interconnection and access to Greek infrastructure were also important. Some of those contacts subsequently continued through working meetings and a field visit in Macedonia.
The memorandums we have signed encompass several partnerships: with Serbia for the construction of the gas interconnector, with Kosovo for cooperation in energy, mining, and mineral resources, with the US for the security of natural gas supplies, and with Croatia for cooperation in the energy sector. Each of them establishes a framework for working on concrete joint priorities, from infrastructural connectivity and supply security to knowledge exchange and institutional support.
We have also expanded cooperation with the academic community through memorandums with the Goce Delchev University in Shtip, as well as with FEIT and FINKI at the Ss. Cyril and Methodius University in Skopje. In this way, we create a foundation for joint research, the application of scientific knowledge, and the involvement of young professionals in the sector's development. For me, the value of these memorandums is confirmed through the activities and results that follow signing them.
I would particularly highlight the quadrilateral ministerial format with Greece, Serbia, and Bulgaria. The first meeting of this type was held in May in Athens, and the second in October in Belgrade. Through this, we have established a mechanism through which ministers and operators regularly discuss the same projects and their implementation. We also discussed support from EU partners for our energy priorities before European institutions.
My task is to ensure that Macedonian needs are clearly presented and that what has been agreed upon has a continuation in the work of the institutions. The result should be seen in a better-prepared project, a harmonized cross-border connection, technical assistance, or access to financing.
Over 800 initiatives for energy facilities have been submitted for 2027. How will you ensure that investments in solar, wind, and batteries strengthen the system, and what does the new law on renewable sources bring?
With the new Energy Law, we have established a more orderly model for planning the construction of energy facilities. Through annual plans, we review investment interest within a joint framework alongside system needs. More than 800 initiatives from private and state investors arrived for the 2027 Plan, and we are working on their evaluation.
This shows serious interest, but a submitted initiative is only the beginning of the procedure. It is necessary to verify the documentation, compliance with plans, and connection capabilities. Network operators play a role regarding technical conditions. Our goal is for the investor to know in a timely manner what can be realized, where limitations exist, and what obligations must be fulfilled.
A significant step is also the adoption of the separate Law on the Use of Energy from Renewable Sources. It regulates important issues for producers and consumers, support measures, guarantees of origin, and energy communities. Citizens, municipalities, and companies receive a legal framework for more active participation in the production and use of clean energy.
The law also provides modern support mechanisms, including two-way contracts for market-based adjustment of differences. Their purpose is to ensure greater predictability for investments, with mechanisms that protect the public interest even during high market prices. The next task is the consistent application of the legal framework and functional procedures.
At the solar conference in September, I emphasized that the development of production must go hand in hand with the development of the grid and storage. Solar power plants produce the most during certain hours, while consumption has a different schedule. Battery systems make it possible to save some of that energy for later and improve system flexibility.
During the same period, the financial closure of the first phase of the wind farm near Shtip was marked. Such private investments are part of the broader development of domestic production, and the institutional obligation is to ensure equal rules and compliance with technical and environmental conditions. A predictable procedure is important both for the investor and for protecting the public interest.
How do you connect the major plans for energy transition with the work on the ground and the expertise of domestic professionals?
Energy policy must be based on the actual functioning of the system. That is why it is important to me that my colleagues from the Ministry who work on plans, programs, and procedures have direct contact with engineers, operators, and the people who maintain the infrastructure on a daily basis.
In September, together with employees from the Ministry, we visited the Vrutok Hydro Power Plant. Such visits allow for a better understanding of the technology, the role of hydropower, and the practical challenges faced by the staff. That knowledge is useful for policy preparation and sectoral coordination, while respecting the independent responsibility of companies for their operations.
In the same month, together with our partners, we also reviewed the Investment Platform for a Just Energy Transition. The updated portfolio encompasses 81 projects with a value of approximately EUR 1.77 billion, and financing has been secured for projects worth about EUR 460 million. These are projects in various phases, so our focus is on preparation, mutual harmonization, and tracking implementation.
A just transition also requires attention to people. New technologies bring a need for new skills in grid management, energy storage, digitiziation, and maintenance. That is why we are deepening cooperation with universities and professional institutions and opening up space for young engineers to get involved in the sector.
For me, good policy is one that connects investment, infrastructure, and the knowledge required for it to function. With such an approach, domestic capacity for managing energy development also grows.
What is the scope of support with inverter air conditioners, and what are you fundamentally changing in the protection of households affected by energy poverty?
The support is broader than the September distribution. In March of this year, we began distributing 4,070 vouchers under the Public Call for 2025. The voucher enables the procurement and installation of a 3.5-kilowatt inverter air conditioner with at least an A+ energy class, valued at up to Mden 28,000 denars, without any additional surcharge from the beneficiary.
In September, we also published the lists of over 500 new vouchers under the 2026 Program. These are intended for households with individuals receiving disability allowances and households with children with disabilities receiving a special allowance, in accordance with the program's conditions. These two procedures alone encompass over 4,500 vouchers, the implementation of which is taking place this year.
Here, the Ministry has direct responsibility: from the preparation of the program and the procedure to informing beneficiaries and the conditions for utilizing the support. An allocated voucher must be turned into an installed and functional device in the home. Therefore, we urge the beneficiaries to complete the procedure on time, within the published deadline of October 15.
With the new Energy Law, for the first time, we defined energy poverty, and a methodology for measuring it has also been adopted. Thus, we are establishing a basis for targeting measures according to established needs and indicators. Energy poverty also relates to a family's ability to secure adequate heating and basic energy services, depending on income, expenses, and the condition of the home.
That is why energy efficiency also has social significance. A better device can reduce the energy required for heating and improve living conditions. Our goal is for support to be accessible and correctly targeted, and for its effect to be monitored in the real lives of the beneficiaries.
Why are geological research, the twenty-year strategy for mineral resources, and the protection of the Macedonian ruby important to you, and how do they connect to economic development?
The state needs to have modern and systematic knowledge of its natural wealth. Without such data, it is difficult to make good decisions regarding spatial planning, resource protection, or the possibilities for their sustainable use. That is why we want a more complete geological picture of the entire territory and better cooperation among the institutions that possess this knowledge.
The adopted Strategy for Geological Research and Sustainable Utilization of Mineral Resources for the period 2026–2046 provides a long-term framework for this work. Twenty-year planning is important because research, investments, and resource protection require continuity. With the strategy, we can more clearly connect scientific knowledge, economic needs, and environmental obligations.
Prospection research serves for the initial determination and assessment of geological potential. By itself, it does not represent a decision to open a mine and does not replace the procedures and permits for potential exploitation. That distinction must be clearly explained to citizens so they know which activity is being carried out, what it can show, and what decisions would follow.
In early October, together with the Geological Survey and the Goce Delchev University, we discussed geothermal potential, critical mineral resources, and opportunities for joint research projects through Horizon Europe. We also initiated the preparation of a catalog of mineral resources. The Ministry coordinates the cooperation, while expert and scientific institutions provide the research foundation.
The Macedonian ruby demonstrates how this knowledge can create additional economic value. With the decision dated June 17, the geographical indication "Macedonian ruby" was protected, and in September we continued with activities for expert quality control and special properties. Protected origin and confirmed quality open up opportunities for domestic processors, artisans, designers, and tourist offers.
More broadly, the mining complex also creates work for engineering companies, laboratories, transport, service activities, and domestic suppliers. It is important that a larger portion of the value remains in the country through knowledge, processing, and higher-value products. That development must go hand in hand with appropriate fees for resource use, occupational safety, and compliance with environmental conditions.
Levica explains the motion of no confidence with the assessment that the Ministry has shown no results. How do you respond to them, and what do you consider is omitted from that assessment?
I am sorry that they do not recognize the work that has been done in that assessment. I respect the right to criticism, but the assessment of a ministry should be based on its legal competencies and verifiable results. When the Ministry, ESM, ERC, and agreements from previous periods are mixed together in the same political message, the public receives a false picture of who decides what.
Our work can be concretely verified. A new Energy Law has been adopted, followed by a separate Law on the Use of Energy from Renewable Sources. We have established annual planning for new energy facilities. The twenty-year strategy for geological research and sustainable utilization of mineral resources has also been adopted. These are basic documents that guide the work of the sectors for which we are responsible.
Regarding risk preparedness, we finalized the national assessment of security of gas supply, in accordance with European rules. It examines risks, potential disruptions, and reaction mechanisms. We also drafted the first comprehensive national Hydrogen Study, with support from the European Union, to perceive in a timely manner the opportunities brought by new technologies.
There is also concrete work in infrastructure. After a long-standing halt, the Thessaloniki-Skopje product pipeline is functional again, securing an additional transport option for the supply of petroleum derivatives. The implementation of the electric power interconnection with Albania continues. The gas interconnector with Greece is under construction, the contract for the Macedonian section of the connection with Serbia has been signed, and joining the Vertical Corridor gives a broader regional perspective to these investments. Companies realize the projects, while the Ministry performs its legal, coordinating, and international role.
International work is also visible. We have signed memorandums with Serbia, Kosovo, the USA, and Croatia, and through memorandums with universities and faculties, we have deepened cooperation with the academic community. We have strengthened cooperation with UN bodies and the Energy Community and established a regular ministerial dialogue with neighboring countries. At the same time, we are implementing programs for vulnerable consumers and working on better control over the use of natural resources.
There is also another important context. We built this Ministry from the very beginning. In the first few months, we did not even have our own building. We had to secure space, form teams, establish the organization, and create technical and administrative conditions for work. An institution with such competencies requires professional people, equipment, procedures, and functional systems. At the same time, obligations toward citizens, companies, and international partners continued every day.
So, when we speak about what has been accomplished, we must also recognize the creation of the institutional capacity that will serve the state in the long term. In September, the Ministry achieved 100 percent according to the Active Transparency Index of the Center for Civil Communications. That is a concrete assessment of proactive information disclosure and an obligation to maintain that standard.
I am ready for a serious parliamentary debate and for accountability regarding every decision within my competence. But the claim that there are no results cannot stand if one examines the laws, programs, documents, and projects that have been set in motion. Data and clear institutional footprints exist for all of them.
The accusations mention an ESM debt higher by EUR 17 million, its tenders, and the 9.9 percent margin of the universal supplier. Can these issues be attributed to you as direct responsibility?
Decisions that I do not make and procedures in which I have no legal right to manage cannot automatically be attributed to me. ESM has a Management and Supervisory Board, and ownership rights are exercised by the Government. The competent bodies of the company are responsible for its procurement, contracts, financial liabilities, and sales offers. The law requires the Ministry, as the owner of the transmission operators, to be separated from the management of the producer.
Regarding the figure of EUR 17 million, an exact financial comparison should be requested from ESM: what period it refers to, what liabilities are included, and what caused the change. That is the way to establish the facts. Simply stating an amount in a party press release establishes neither a cause nor the personal responsibility of the Minister.
Regarding the universal supplier, the chronology is also important. The Government's decision to select EVN's bid was made on April 16, 2024, prior to the formation of this Ministry and before I took office. The 9.9 percent margin stems from the tender procedure for selecting a universal supplier. That is a gross supply margin, which should not be equated with the company's net profit. I did not set that margin.

And regarding prices, the division of roles must also be respected. ESM forms its electricity supply offer, and ERC exercises its statutory regulatory powers regarding tariffs and the verification of the universal supplier's calculations. The Ministry does not determine the final price of electricity for households and must not dictate independent regulatory decisions.
My attitude toward the control of public funds is clear. Right after taking office, I requested checks by the State Audit Office in the sector. In September, with Chief State Auditor Maksim Acevski, we reviewed the findings and the need for the recommendations to be given concrete measures, deadlines, and responsible persons. Requesting an independent check is part of responsible action within institutional powers.
I am open to a dialogue based on documents. But I do not accept that someone else's tenders or decisions made prior to its formation be attributed to this Ministry. Responsibility must be determined according to the law, the specific procedure, and the persons who made the decisions.
Levica also claims that concession fees are low and that citizens are not being listened to during geological research. What does your handling of this area show?
First, we increased concession fees by up to 100 percent with the new tariff schedule that has been applied since January 1, 2025. We have strengthened controls and actions against concessionaires who do not fulfill their obligations. There are already over 40 revoked concessions due to established irregularities. This shows that the use of natural resources is tied to obligations that must be met.
The result is also visible in the collection. In 2025, over Mden1.22 billion were collected on the basis of exploitation concession fees, compared to about Mden 561.5 million in 2024. That is more than double the collection. In the first half of 2026, the collection amounts to about Mden 573.9 million, which means that the higher level achieved after the changes is being maintained.
For us, it is fundamental that everything used from Macedonia's natural wealth is appropriately paid for and that environmental protection conditions are respected. Paying a fee does not exempt anyone from environmental obligations. Controls, verification of contracts, and action regarding irregularities must go hand in hand.
Regarding geological research, citizens have the right to a clear explanation. Research should provide us with knowledge of what we possess as a state. It does not automatically grant the right to open a mine. Separate procedures and conditions exist for potential exploitation, including those concerning the environment and public participation.
With the drafting of legislation for geology and mining, we are also working on clearer rules. More practical workshops are needed with municipalities, the professional public, companies, and civil society organizations, in cooperation with European partners as well. People need to understand in a timely manner what is changing, which institution is competent, and how they can participate in the procedures.
Transparency here is essential. Which is why registries and information regarding concessions are published, and institutions are expected to provide reasoned responses for each specific case. Development makes sense when it creates work and revenue for the country, through responsible resource use and respect for the people living in those environments. That is the approach we are implementing and for which I am ready to account.